Hi All

Monday 25thMarch 2019:
Off to see the bamboo furniture people this morning. They have completed our bed, 1 x couch and a bench for the end of the bed. Looks great. Organised transport to the block where it is being stored in the Italian place next door (where we stored our building materials).

Had a win today. For the first time in 4 months I was able to have a cup of tea with real milk (well, long life milk from NZ). And it was damn good. Dairy is almost non-existent here on the island so it was a real bonus to find 2 litres of the milk at the local “supermarket”.

We have been using powdered milk which isn’t too bad as we found a good one. But it is nothing like the real milk.

Tuesday 26thMarch 2019:

Off to the block and meet the cushion maker. Our bamboo furniture arrived yesterday and is being stored in the Italian house next door (bed, couch & bench). The cushion maker measured up the couch as we are getting a padded seat, backrest pillows and loose pillows.

Also discussed the next week’s work onsite. Lots still happening.

Ruby had surgery this morning. The previous puncture fix started leaking. So found a tire repair man just down the road who does tubeless tires and all good. Cost P100 – $2.70 AUS.

After lunch Guy off to Mahjong and I went for a ride to see Ron (American). He is going blind so loves to see visitors for a chat.

Wednesday 27thMarch 2019:

The front fence construction started today. It will be a bamboo fence made from the old scaffolding and some new bamboo cut from our block up by the main road.

Guy off to Mahjong after lunch. I had my siesta and then went for a ride down the coast exploring on Ruby.

Thursday 28thMarch 2019:

Meet with the carpenter this morning and ran through the kitchen benches and island and shelving requirements. He starts his construction on Monday.

Friday 29thMarch 2019:

Meet with Marelco (power provider) re getting the power to our house. As we are 100m + from the main road/power line, we need to install 3 power poles for the wires to our house (at our cost). Also got to pay for the extra cable as you only get 30m from the main lines.

Got our foreman organised to get the poles installed by tomorrow. Back to Marelco Monday to pay the extra cable fee and then hopefully get the power hooked up by the end of the week.

After lunch Guy off to Mahjong and I went for a ride to catch up with Gerald (Pom) for a chat.

Saturday 30thMarch 2019:

Quick trip to the block first thing in the morning. Then back at 4:00pm to pay the boys and contractors.

On the way home we dropped into the furniture man and saw our Acacia coffee table. This coffee table was made from the big Acacia tree we had to cut down for the house.

They did an awesome job and it is stunning. We have an 8-seater dining room table still to come made out of the same tree.

Finished the day with a 2 hour massage each.

Sunday 31stMarch 2019:

We enjoyed our regular Sunday manicure/pedicure this morning. Then off to a local canteen for a treat of burgers and fries for lunch.

Guy off to Mahjong and I had a relaxing afternoon defrosting our apartment’s bar fridge. The freezer section was a huge block of ice and took hours to defrost.

Life is good.

Trevor & Guy

Advertisements

Day 647 of retirement

March 24, 2019

Click on a photo below for the slide show. The slide show has the descriptions of each pic below the photos. You can also leave comments in this area.

To view the full-size photo in a separate window, go to the bottom right hand corner of the photo info and click on “View full size”. You can download the photo from this window if you wish.

Hi All

Tuesday 19thMarch 2019:
Back to the Marelco office (in Buenavista) this morning with all the correct paperwork for our power connection to the house. We were missing a couple bits of paperwork yesterday.
Our electrical engineer confirmed later in the day that all is now good.
We get an inspection on Monday and then the connection to follow. So now looks like a week or two to get power.
The boys started the hollow block fence round the top of the roof. Electrical, plumbing, tiling and painting still in full swing.

After lunch Guy off to Mahjong. I had my afternoon siesta, went TV shopping (surprisingly they had a good (limited) selection), had my afternoon walk around the town and lastly picked up a few supplies at the market.

Wednesday 20thMarch 2019:

Met with our wooden door man this morning and inspected our handmade wooden doors (5 of). Awesome job. Will install when the painting is finished. A few weeks away yet.
Also ordered a handmade wooden TV stand to match the doors and 4 engraved panels for the kitchen island.
Then meet with our table and chairs man. Also coming along very nicely. These are being made from the wood from a tree on our block.
Tiling now starting on the lounge/kitchen. The boys are also still working on the two bathrooms at present.

Thursday 21stMarch 2019:
The clean-up of the front yard has started. All the old scaffolding is in the process of being moved out the back and the materials no longer useful are being burnt.
The front bamboo fence has now been pegged and is about to be started. We have decided to fence the block with a bamboo fence for now. Once we get a car and the landscaping plan sorted, we will then put up a hollow block fence (in a year or so).

Guy off to Mahjong after lunch and I did my usual siesta, market run and walk.

Friday 22ndMarch 2019:

The stairs’ stainless steel handrail commenced installation today. All being fabricated/assembled onsite.
After lunch I dropped into Gerald’s (Pom). He has 10 orphaned piglets. Sadly, the mother died giving birth on Monday. So, every 2 hours he is up feeding them.
I now know why I will never have a piggery.

Saturday 23rdMarch 2019:

The stairs’ stainless steel handrail is now being manufactured and installed.
All other work continuing full steam ahead (tiling, painting, rendering, plumbing, electrical and pump shed).

No Mahjong today as payday for the boys. Guy also has a touch of the flu so a very nice siesta/rest afternoon was had by all.

Finished off the day with a 2-hour massage each in the evening. (P350 = $9.46 each).

Sunday 24thMarch 2019:

Rest day today. No workers.

Guy and I enjoyed a manicure/pedicure each in the morning with Josefin (P120 each $3.16 AUS).

After lunch Guy off to Mahjong and I had my siesta and walk around the town. Then gave Ruby a service and check over.

At 6:00pm we were off to our friend Gil’s birthday party.

Life is good.

Trevor & Guy


Day 640 of retirement

March 17, 2019

Click on a photo below for the slide show. The slide show has the descriptions of each pic below the photos. You can also leave comments in this area.

To view the full-size photo in a separate window, go to the bottom right hand corner of the photo info and click on “View full size”. You can download the photo from this window if you wish.

Hi All

Monday 11thMarch 2019:
Early start at the block as we need to peg out the electric pump shed so the boys can start building.

Originally, we were going to have a separate pump and generator sheds but have now combined the two. The single shed will be for the electric pump for the well plus pressure tank, the generator, a Ruby garage and building supplies storage.

The painters also started and will be painting (5 coats) the two guest bedrooms first.

At 4:00pm we headed back to our next-door neighbours as it is Semie’s 50thbirthday party. Awesome neighbours Semie and Ben (French Canadian).

Tuesday 12thMarch 2018:

Out to the block and met with the electrician. We then followed him into Buenavista (4km) to the Marelco office (electricity supplier) to get the paper work under way for connecting the power. More paperwork.

After lunch Guy off to Mahjong and I caught up with John (Pom).

Wednesday 13thMarch 2019:

Another busy day at the construction site. Awesome supervision by our foreman Franie. Keeps everything/everybody organised and coordinated.
Painting concrete here consists of:
~ Washing the walls with a cleaning agent
~ A white filler coat (Putty like)
~ A Water proofing coating (Outside only)
~ A primer coat
~ 3 x Main coats of paint

Thursday 14thMarch 2019:

Work, work, work. No rest for the wicked.

AM block visit. Guy off to Mahjong after lunch. I had my siesta and then my afternoon walk around the town.

Friday 15thMarch 2019:

Got our building permit up today. Only 3.5 months since we applied. Guess we can start building now.

Off to the Marelco office in Boac (capital) to get the power meter box for our supply post. Then to the Marelco office in Buenavista to apply for a connection. We were missing a couple bits of paper work so back on Monday with all the requirements.

Guy off to Mahjong after lunch and I had my usual siesta and walk around the town.

Saturday 16thMarch 2019:

Quick trip to the block in the morning. Then back at 4:00pm as it is payday for the boys.
We both were pampered today with a foot spa (P200 = $5.40 each) each in the morning followed by a 2-hour massage each in the evening. (P350 = $9.46 each).
No Mahjong today for Guy.

Sunday 17thMarch 2019:

Rest day today. No workers.

We both had our standing manicure/pedicure in the morning. After lunch Guy off to Mahjong and I had my siesta and then gave Ruby a service and check over.

Life is good.

 

 


Day 633 of retirement

March 10, 2019

Click on a photo below for the slide show. The slide show has the descriptions of each pic below the photos. You can also leave comments in this area.

To view the full-size photo in a separate window, go to the bottom right hand corner of the photo info and click on “View full size”. You can download the photo from this window if you wish.

Hi All

Monday 4thMarch 2019:

At 7:00am Guy, John and I went for our regular Monday morning walk before it got too hot and humid. Then back to the block as installation of plumbing, electrical, ceiling and more concreting happening.

Tuesday 5thMarch 2019:

Block visit as things are rapidly progressing.

After lunch Guy off to Mahjong and I managed my afternoon siesta.

Wednesday 6thMarch 2019:

Tiling has commenced in the two guest bedrooms.
Stairway to the roof form work/scaffolding going up.
Veranda concrete being completed.
Electrician, plumber and ceiling works continuing.

Guy off to Mahjong after lunch and I had my siesta and then caught up with John (Pom).

Thursday 7thMarch 2019:

Meet up with John (Pom) and we rode out to see Gerald (Pom) for a catch up.

Back to Gasan and picked up Guy and off to the block for our daily inspection.

Lunch time Guy was off to Mahjong and I had my usual siesta and walk to the market for some fruit.

Friday 8thMarch 2019:

Tiling coming along nicely. 1 guest bedroom done and 2nd one not far behind. Move to master bedroom tomorrow.
Ceiling going up in master bedroom/bathroom.
Back veranda concrete pour today.
Stairs to roof form work/reinforcing well underway.
Plumber & electrician working round all the above works.
Painting starts Monday on guest bedrooms.

Quick trip to the bank in Boac (40km) to get some cash to pay the boys tomorrow. After lunch Guy off to Mahjong and I had my siesta.

At 5:00pm we made our way to Buenavista (15km away and just past our block) to meet up with Susan who owns the block next to ours that we have been using as storage facility. Had a very nice dinner with Susan, Racky (traveling friend) and Semie our neighbour.

Saturday 9thMarch 2019:

We now have stairs to the roof. Tiling in the master bedroom underway.

No Mahjong today. Rest day.

Pay day for the boys at 4:00pm. Another awesome week.

Finished off the day with a two-hour massage each.

Sunday 10thMarch 2019:

Rest day today as the boys have the day off.

Enjoyed our regular pedicure/manicure this morning.

After lunch Guy off to Mahjong and I enjoyed my siesta.

I played round with sizing for the pump/storage shed as the boys want to start building tomorrow. Also looked at some designs for the hollow block wall on the roof edge.

Caught up with John (Pom) for an afternoon coffee/tea.

Life is good.

Trevor & Guy

 


Day 626 of retirement

March 3, 2019

Click on a photo below for the slide show. The slide show has the descriptions of each pic below the photos. You can also leave comments in this area.

To view the full-size photo in a separate window, go to the bottom right hand corner of the photo info and click on “View full size”. You can download the photo from this window if you wish.

Hi All

Tuesday 26thFebruary 2019:
Rendering of the walls in full swing. Should be finished by the end of the week.
Window man here tomorrow to measure up.
Ceiling man back tomorrow to start in the guest bedrooms (waiting on materials).
Plumber and electrician working on their installations.

Guy off to a birthday party late morning then Mahjong.

I had my afternoon siesta and then a walk around the town.

Thursday 28thFebruary 2019:

Off to Boac (40km round trip) to see the window man after his visit to the site yesterday to measure up all the doors and windows. He had a contract prepared which lists all the work required.

He showed us some samples of the materials he will use and we then paid half the contract price. We pay the rest on installation.

Lunch in Boac and then Guy off to Mahjong for the afternoon.

I went for a ride to the block to check out progress. Once back in Gasan did my fresh food shop at the market. Snuck in a little siesta as well.

Friday 1stMarch 2019:

The concrete floor for the passageway, kitchen/lounge poured today.
Ceiling installation is underway. Also agreed on the painting (inside & out) contract cost (same people as ceiling installers).
Plumber installing water and drainage pipes.
Outside rendering being completed.
Bamboo furniture people inspected our old scaffolding bamboo and will take it to build our furniture (bed, bed side tables, 2 x couches, bench at end of bed). Agreed on price for all the furniture.
All happening.

After lunch Guy off to Mahjong, I had my siesta and then caught up with John (Pom).

Saturday 2ndMarch 2019:
Another busy week comes to an end.
80% of internal concrete floors poured.
Ceiling in two guest bedrooms installed.
Concreting the outside verandas next week.
Meet with carpenter re kitchen cupboards. All good.
Time for a cup of tea and a lay down.

Sunday 3rdMarch 2019:

Went for a hike today with John (Pom) while Guy played Mahjong. John lives at the end of a road with a ridge-line rising up. We climbed up the side, hiked along the ridge and then back down to his place (1.5 hours).
One of the great things about Marinduque you can hike for an hour and be in beautiful jungle with no people.

Life is good.

Trevor & Guy